Namibia has ambitious plans to address its housing shortage. Thousands of residential plots have been targeted for development across the country, and billions of Namibia dollars have been allocated towards land servicing and housing infrastructure.
But a recent parliamentary response has brought an important challenge into focus.
According to Urban and Rural Development Minister James Sankwasa, not a single fully serviced residential plot has yet been delivered under the government’s current land-servicing programme, despite a target of 17 000 plots across 11 local authorities.
The estimated cost of the programme exceeds N$ 2 billion.
This raises an important question for the property industry:
If the demand for housing exists and land has been identified, why is getting that land ready for development still such a challenge?
The 17 000-plot target
The government programme covers 11 local authorities, with the largest allocation being 5 000 plots for Windhoek.
The remaining ten local authorities have targets of 1 200 plots each.
The programme includes:
Town Target plots
| Windhoek | 5 000 |
| Walvis Bay | 1 200 |
| Keetmanshoop | 1 200 |
| Rundu | 1 200 |
| Oshakati | 1 200 |
| Usakos | 1 200 |
| Bukalo | 1 200 |
| Katima Mulilo | 1 200 |
| Mariental | 1 200 |
| Otjiwarongo | 1 200 |
| Swakopmund | 1 200 |
|
|
|
| Total | 17 000 |
The Minister explained that the targeted plots are at different stages of infrastructure development, but none had yet received all the necessary services: water, sewerage, electricity and roads.
The Ministry had initially expected the servicing programme to be completed by December 2026. However, cash-flow constraints and insufficient funding have delayed implementation.
The challenge is infrastructure, not simply land
For property development to take place, identifying available land is only the beginning.
A residential plot needs the necessary infrastructure before it can be properly developed and occupied.
This includes:
· Water connections and reticulation
· Sewerage infrastructure
· Electricity supply
· Access roads and associated infrastructure
These services require substantial investment, planning and coordination between government departments, local authorities and service providers.
The Minister acknowledged that the Ministry’s N$ 1.2 billion capital budget for the 2025/26 financial year was insufficient to provide the bulk infrastructure requirements for the programme.
He also highlighted the affordability challenge in informal settlements, where residents often cannot contribute towards the cost of infrastructure, leaving government funding as the primary source of financing.
This illustrates why land servicing remains one of the most important, yet often overlooked, parts of the housing-delivery process.
Housing is being delivered, but the land-servicing challenge remains
It is important to recognize that the latest announcement does not mean that no housing process is being made in Namibia.
In the same parliamentary response, the Minister reported that 1 112 housing units were completed during the 2025/26 financial year.
A further 1 575 units were recorded during the first two quarters of the 2026/27 financial year.
This brings reported housing delivery across those periods to 2 683 units.
The figures include both new housing developments and informal settlement upgrading initiatives.
Another 304 housing units are under construction at Otjomuise Extension 10 in Windhoek, with completion expected by the end of December 2026.
These developments demonstrate that housing delivery is continuing through various programmes and partnerships.
However, completed houses and fully serviced residential plots are two different measures of progress. Both are necessary if Namibia is to expand its formal housing supply sustainably.
What does this mean for the property market?
The implications extend well beyond government housing programmes.
For developers
The availability of properly serviced land is essential to development feasibility. Without it, even developers with access to finance and construction capacity may struggle to move projects forward
For landowners and investors
Serviced land becomes an increasingly important asset in a market where infrastructure provision is a major constraint. However, the value of land must always be considered in relation to its location, zoning, servicing status and actual development potential.
For homebuyers
A shortage of serviced plots limits the opportunities available to people who want to build their own homes. It can also restrict the supply of new housing entering the market.
For property professionals
Understanding where land is available, what infrastructure is in place and which developments are likely to progress is becoming increasingly important when advising clients and assessing market opportunities.
What happens next?
The government’s stated target is to complete the servicing works by December 2026.
With the programme still facing funding and implementation constraints, the coming weeks will be important in determining how much progress can realistically be achieved.
At Step Up Properties, we will be watching for tangible progress in the delivery of serviced land, particularly in Windhoek, Walvis Bay and other targeted towns.
We will also be following how government addresses the funding and coordination challenges that continue to affect land development.
The bigger picture
Namibia’s housing challenge cannot be solved by setting targets alone.
Land must be identified, infrastructure must be provided, funding must be secured and development must move through the necessary planning and approval process.
Until these elements come together, the gap between planned housing supply and actual delivery is likely to remain.
Because land on a development plan is not the same as land ready for a home.